0915406 B.C. Ltd. et al. v. 0834618 B.C. Ltd. et al., [2013] B.C.T.C. Uned. 1099
Jurisdiction | British Columbia |
Court | Supreme Court of British Columbia (Canada) |
Judge | Fisher, J. |
Citation | [2013] B.C.T.C. Uned. 1099,2013 BCSC 1099,[2013] B.C.T.C. Uned. 1099 (SC) |
Subject Matter | SALE OF LAND,CONTRACTS,FRAUD AND MISREPRESENTATION |
Date | 21 June 2013 |
-
- This document is available in original version only for vLex customers
View this document and try vLex for 7 days - TRY VLEX
- This document is available in original version only for vLex customers
8 practice notes
-
Table of cases
...OF CASES 0867740 BC Ltd v Quails View Farm Inc, 2013 BCSC 1021 ...............................110 0915406 BC Ltd v 0834618 BC Ltd, 2013 BCSC 1099 ................................525, 531 100 Main Street Ltd v WB Sullivan Construction Ltd (1978), 20 OR (2d) 401, 88 DLR (3d) 1 (CA) ................
-
Judicial Oversight of Remedy Stipulation
...to the plaintiff. To give the plaintiff only its loss of net profits would not compensate the 13 In 0915406 BC Ltd v 0834618 BC Ltd , 2013 BCSC 1099 [ 0915406 ], the amount stipulated in the contract as liquidated damages, $300,000, was held to be a genuine pre-estimate of damages in a real......
-
0856464 B.C. Ltd. et al. v. TimberWest Forest Corp. et al., [2014] B.C.T.C. Uned. 2433 (SC)
...a positive assertion or tacitly confirms a false one may found a cause of action in deceit": 0915406 B.C. Ltd. v. 0834618 B.C. Ltd. , 2013 BCSC 1099 at para. 107 [316] However, I agree with the defendant that the claim for fraudulent misrepresentation fails on the evidence. [317] The timing......
-
0915406 B.C. Ltd. et al. v. 0834618 B.C. Ltd. et al., [2013] B.C.T.C. Uned. 1529
...for completion, 083 sold the land to a third party. The background facts and the legal and factual issues are set out in my reasons at 2013 BCSC 1099, so I will not repeat them here. [3] The plaintiffs seek an order that 083 pays the costs of 388 at Scale B and that Mr. Minhas either bear h......
Request a trial to view additional results
6 cases
-
0856464 B.C. Ltd. et al. v. TimberWest Forest Corp. et al., [2014] B.C.T.C. Uned. 2433 (SC)
...a positive assertion or tacitly confirms a false one may found a cause of action in deceit": 0915406 B.C. Ltd. v. 0834618 B.C. Ltd. , 2013 BCSC 1099 at para. 107 [316] However, I agree with the defendant that the claim for fraudulent misrepresentation fails on the evidence. [317] The timing......
-
0915406 B.C. Ltd. et al. v. 0834618 B.C. Ltd. et al., [2013] B.C.T.C. Uned. 1529
...for completion, 083 sold the land to a third party. The background facts and the legal and factual issues are set out in my reasons at 2013 BCSC 1099, so I will not repeat them here. [3] The plaintiffs seek an order that 083 pays the costs of 388 at Scale B and that Mr. Minhas either bear h......
-
Deol v. Sinnathamby,
...purchase, they are in essential default and cannot succeed in an action for specific performance: 0915406 B.C. Ltd. v. 0834618 B.C. Ltd., 2013 BCSC 1099 at para. [46] The requirement for a plaintiff seeking specific performance to show their willingness and ability to perform on the contrac......
-
Save-A-Lot Holdings Corp. v. Christensen,
...they fit into a pre-determined category. [54] See also 0915406 B.C. Ltd. v. 0834618 B.C. Ltd., 2013 BCSC 1099 at para. 107, per Madam Justice 107 As a general rule, mere silence cannot form the basis for a misrepresentation, but active co......
Request a trial to view additional results
2 books & journal articles
-
Table of cases
...OF CASES 0867740 BC Ltd v Quails View Farm Inc, 2013 BCSC 1021 ...............................110 0915406 BC Ltd v 0834618 BC Ltd, 2013 BCSC 1099 ................................525, 531 100 Main Street Ltd v WB Sullivan Construction Ltd (1978), 20 OR (2d) 401, 88 DLR (3d) 1 (CA) ................
-
Judicial Oversight of Remedy Stipulation
...to the plaintiff. To give the plaintiff only its loss of net profits would not compensate the 13 In 0915406 BC Ltd v 0834618 BC Ltd , 2013 BCSC 1099 [ 0915406 ], the amount stipulated in the contract as liquidated damages, $300,000, was held to be a genuine pre-estimate of damages in a real......