H.T. Drywall Ltd. v. Carriage Holdings Ltd., (1979) 24 A.R. 68 (QB)

JudgeWaite, J.
CourtCourt of Queen's Bench of Alberta (Canada)
Case DateNovember 29, 1979
Citations(1979), 24 A.R. 68 (QB)

H.T. Drywall Ltd. v. Carriage Holdings (1979), 24 A.R. 68 (QB)

MLB headnote and full text

H.T. Drywall Ltd. v. Carriage Holdings Ltd.

(Q.B. 127700)

Indexed As: H.T. Drywall Ltd. v. Carriage Holdings Ltd.

Alberta Court of Queen's Bench

Waite, J.

November 29, 1979.

Summary:

This headnote contains no summary.

Contracts - Topic 3664

Performance or breach - Repudiation - What constitutes - A general contractor asked for and accepted the plaintiff contractor's tender on a construction project - The contractor's tender contained a clause allowing price increases to be passed on to the general contractor - The work contract contained a price escalation clause for changes agreed upon by the parties - Prior to work commencement the contractor sent a letter to the general contractor attempting to increase the contract price - The general contractor believed the letter was a repudiation so replied by cancelling the contract - The contractor brought an action against the general contractor for improper cancellation of the contract - The Alberta Court of Queen's Bench allowed the action and held that the contractor's letter was not a repudiation, but rather a unilateral attempt to change the contract - The Queen's Bench further held that the general contractor's letter was a repudiation for which the contractor could recover damages - See paragraph 15.

Contracts - Topic 3666

Performance or breach - Repudiation - Acceptance of repudiation - What constitutes - A contractor attempted to unilaterally increase the price of a contract with a general contractor - The general contractor cancelled the contract - The contractor made one unsuccessful attempt to obtain a reason for cancellation and then commenced an action for damages for breach of contract by the general contractor - The Alberta Court of Queen's Bench allowed the action and held that the general contractor's repudiation was so absolute that a notice of acceptance by the contractor was not necessary - The Queen's Bench further held that the contractor's passive reaction to the repudiation was not a bar to the contractor's right to recover for breach of contract - See paragraph 15.

Contracts - Topic 4023

Remedies for breach - Damages - Extent of liability - Losses attributable to breach - A contractor's tender for a construction project was accepted - Because of the size of the project, the contractor hired extra personnel and arranged to be without other projects for the four months necessary to complete the contract - The general contractor repudiated the contract before the contractor commenced work - The contractor was unable to obtain other projects during the four month period - The contractor brought an action to recover gross profits being 15% of the contract price and including overhead and net profit usually earned on such a project - The Alberta Court of Queen's Bench allowed the action and held that the contractor could recover gross profits lost because of the general contractor's repudiation - See paragraphs 10 to 16.

Cases Noticed:

Dawson v. Helicopter Exploration Co. Ltd., [1955] 5 D.L.R. 404, refd to. [para. 15].

Authors and Works Noticed:

Chitty on Contracts (24th Ed.), paragraphs 1479, 1480 [para. 13].

Counsel:

G.F. Graham, for the plaintiff;

R.D. Ghitter, Q.C., for the defendant.

This case was heard by WAITE, J., of the Alberta Court of Queen's Bench.

On November, 29, 1979, WAITE, J., delivered the following judgment.

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT