TRANSITIONAL MATTERS - RENEWABLE ENERGY GENERATION FACILITIES, O. Reg. 121/19

JurisdictionOntario

Planning Act

ONTARIO REGULATION 121/19

TRANSITIONAL MATTERS - RENEWABLE ENERGY GENERATION FACILITIES

Consolidation Period: From June 1, 2019 to the e-Laws currency date.

No amendments.

This is the English version of a bilingual regulation.

Transition, s. 62.0.2 of the Act

1. (1) Subject to subsection (4), section 62.0.2 of the Act, as it read immediately before its repeal by subsection 8 (9) of the Green Energy Repeal Act, 2018, applies to a renewable energy generation facility if,

(a) a renewable energy approval mentioned in subsection 47.3 (1) of the Environmental Protection Act was issued in respect of the facility before the day section 62.0.2 was repealed and was still in effect on that day;

(b) the facility is the subject of a contract under the Feed-in Tariff (FIT) Program, microFIT Program, Large Renewable Procurement (LRP), Renewable Energy Supply program or Renewable Energy Standard Offer Program (RESOP) that was entered into before the day section 62.0.2 was repealed and no party to the contract had exercised a right to terminate the contract before that day; or

(c) subject to subsection (2), the construction or installation of the facility began before the day section 62.0.2 was repealed and is completed before August 31, 2019.

(2) For the purposes of clause (1) (c), if any contracts were awarded for carrying out any part of the construction or installation, construction or installation is deemed to begin on the day on which the first contract was awarded.

(3) The owner of a renewable energy generation facility referred to in clause (1) (c) shall maintain such records as are necessary to show the date on which construction or installation of the facility began and the date on which construction or installation of the facility was completed.

(4) If a renewable energy generation facility mentioned in subsection (1) is subject to an extension, alteration, renovation or addition, section 62.0.2 of the Act, as it read immediately before its repeal by subsection 8 (9) of the Green Energy Repeal Act, 2018, continues to apply to the facility in accordance with the following rules:

1. If the facility is not the subject of a renewable energy approval mentioned in subsection 47.3 (1) of the Environmental Protection Act or an approval, registration or permit set out in subsection (5), section 62.0.2 of the Act continues to apply to the entire facility.

2. If the facility is a facility mentioned in clause (1) (a), section...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT