Aecon scores $85-million Vale contract.

PositionAROUND THE NORTH - Aecon Group Inc. snags Vale's Clean Atmospheric Emissions Reduction project - Brief article

Aecon has been awarded an $85-million contract for site preparation and foundation construction for Vale's Clean Atmospheric Emissions Reduction (AER) project in Sudbury.

Aecon's work will mark the first phase of the $2-billion, three-year project, which is expected to reduce Vale's smelter emissions by 70 per cent from current levels, and reduce dust and metals emissions by 35 to 40 per cent, when complete by the end of 2015.

The first phase of the project includes construction of reinforced concrete foundations, pipe rack foundation and site preparation work for the process plant, as well as detailed excavation and backfill for these structures.

"Aecon looks forward to bringing our heavy civil expertise to this sustainable mining project for Vale," Ten...