Falco moves to prefeasibility stage on Nickel Rim.

AuthorWareing, Andrew
PositionMining Around the North - Falconbridge Ltd. assesses Nickel Rim South property

There are many more steps to be taken by Falconbridge Ltd.'s geologists before development of the Nickel Rim South property can become a full-fledged mine.

"We are in the midst of a geotechnical drilling program" as part of pre-feasibility assessment for the digging of an exploratory shaft, says Mike Welch, Falconbridge's manager of geology in Sudbury.

Welch says that the work being done establishes several critical criteria before further exploration work can be done underground. It is part of a careful, multi-step capital request process adopted by Falconbridge since its integration with Noranda.

"It's not like the old days when we used to say, 'Here's the project, it's going to cost us $500 million, please give us the money.' Now, we have to do it in a series of steps," he says.

The site, located two kilometres north of the Greater Sudbury Airport, is being looked at because of the discovery nearly two years ago of high grades of nickel, copper and platinum-group metals. Current data indicates 3.8 million tonnes of ore in the footwall zone consisting of 1.7 per cent nickel, 5.1 per cent copper, 0.02 per cent cobalt, 2.3 grams per tonne of gold, 3.3 grams per tonne of platinum and 3.8 grams per tonne of palladium.

In...